Well ladies and gents, it’s been a long one. But somewhere in between day jobs and all other tasks, Ryan managed to frame out the guest bathroom.photo(6) Big things coming up (and in order)…

1. Complete trim on roof

2. Prep and install all windows and exterior doors

3. Install soffits and siding

4. Plumbing and electric

5. Insulation

6. Drywall

The plan is to have this list completed within the next 6 weeks. Well, enough chit chat, it’s work time!

 

 

 

 

 

 

 

 